The short answer: a change request is any request that alters a signed deliverable, acceptance criterion, assumption or date, and it needs a price and a written approval before anyone builds it. A bug against agreed behaviour is not a change request; it is a defect the contract already covers. That distinction is what keeps a fixed price fixed.
Most scope disputes are not about engineering; they are about whether something was "in the original scope", argued months after anyone last read it.
What counts as a change request
A change request is a formal request to alter the agreed baseline. The test: would the statement of work read differently if it were written today?
- It is a change: a new report or module, a different payment provider, a data source nobody listed, a design change after sign-off, a deadline pull-in that needs more people.
- It is not a change: a defect in delivered work, a requirement clarified inside the feature already sold, a configuration setting, content within the agreed volume.
- It is a judgement call: "make it faster" with no performance criterion written. Whoever wrote the acceptance criteria decides, which is why vague criteria cost money later.
The four questions every change request must answer
A usable change request is a short record, not an email thread.
- What changes. Named precisely enough that two people would build the same thing: not "better reporting" but "a monthly revenue report by client, exportable to CSV".
- Why now. What stays blocked if this waits. That separates a requirement from a preference, and it is usually answered badly when nobody asks.
- What it displaces. A team of fixed size has fixed capacity. Anything added either moves a date or replaces planned work; a request claiming neither is borrowing somebody's evenings.
- What it costs. Hours by role, date impact, and the assumptions the estimate rests on. One number with no range is a guess wearing a suit.
Three ways to price a change
No single model is correct. Each shifts risk differently; match it to how often changes arrive and how well the work can be estimated.
| Model | Priced as | Fits | Fails when |
|---|---|---|---|
| Unit rate | Rate per day or role, applied to a small/medium/large band | A steady stream of small changes, no renegotiation each time | The bands are wide, so a one-hour change bills at the small-band ceiling |
| Time and materials | Actual hours at a blended rate, with a written cap per change | Changes whose shape is unknown until work starts, such as third-party APIs | Nobody watches the hours and the change becomes an open tab |
| Trade against the backlog | Equal-effort swaps inside an agreed release capacity | Products with a real backlog and a client who can drop items | The swapped-out item is never dropped, so capacity grows for free |
Most engagements use two: a unit rate for small changes the product owner approves alone, and a full estimate for anything touching the data model, a third party or the date. Fixed price versus time and materials governs the base contract; the change model governs everything after signature.
Price the ripple, not the ticket
A change is never priced by the hours spent typing the new screen. It is priced by everything it touches downstream — which is where a two-day estimate becomes a two-week reality.
Take a field added to an order. Nobody needs two days for the input. They need time to migrate existing rows, choose a default for historic orders, update everything that reads the order, test every role that can see it, and release without breaking a report. Multiply that across a data model or permission change and the real cost appears.
Ask for the ripple as line items: schema and migration, consumer updates, regression testing, documentation, release and rollback. A one-line estimate is a floor, not a price.
Change control that survives a real project
Change control fails when it is heavy enough that people route around it. Keep it to one form, one approver, one weekly cut-off, and nothing built before written approval.
- One log where the work lives. Ticket id, requester, date, estimate, approver. A spreadsheet nobody opens is not a log.
- A named approver with budget authority. Not necessarily the person who asked. Approval from someone who cannot release budget is a wish.
- A threshold the project manager approves alone. State it in hours, so small changes do not wait for a steering meeting.
- An emergency path. Fix a production incident first, paper within one business day. Keep the exception narrow or everything becomes one.
- A date-impact rule. Any approved change that moves a date updates the schedule in the same document.
Log the requests you reject, too. A rejection with a reason ends the "we asked for that in March" conversation before it starts.
What the change log tells you at month end
Read the log as a diagnostic, not a bill. Where changes cluster, who raises them and which assumptions keep failing say more than the total does.
If changes cluster on one module, discovery there was thin. If they cluster around one assumption — "the supplier API returns prices in the same format" — it was never tested before it was priced. If one stakeholder raises nearly all of them, that person was missing from sign-off. Each is a process fix worth more than the fees it caused.
Change as a share of budget is a useful figure but a poor target: a very low share can mean nobody is engaging, and a high share can mean the product got better than the brief. The number that should worry you is unpriced change — work done before a request existed.
How a client should review one
Five checks take two minutes: what is included and explicitly excluded, hours by role plus the ripple, a range with assumptions, the effect on the date, and an expiry on the price.
Then approve it once, in writing, with the price attached. Approval given on a call is the version everyone remembers differently.
Our custom software development services run change control this way from the first sprint; talk to us to have a live change log reviewed.
Frequently asked questions
Is a change request the same as scope creep?
No. Scope creep is unpriced, unapproved work that accumulates quietly. A change request makes it visible, priced and decided. Projects with a working process still have many changes; they just do not discover them at the invoice.
Who should approve a change request?
Whoever holds budget authority, named in the statement of work. If the person requesting cannot approve the cost, the request needs a second signature — otherwise the vendor builds work nobody agreed to pay for.
Can a change request move the deadline?
Only if the approval says so. A change that adds scope without moving the date is a hidden commitment to overtime or to lower quality elsewhere. The date impact belongs beside the price.
What if the vendor calls something a change when you think it was included?
Check the out-of-scope list and acceptance criteria. If neither settles it, the ambiguity was in the document: split the cost and fix the template next time. Arguing costs more than the change.